Skip Navigation

Construction

Max Westheimer Airport, The University of Oklahoma website wordmark
Skip Side Navigation

2018 Projects

Crack and Seal Runway 18/36 Rehabilitation

October 15, 2018 - October 26, 2018

The Crack and Seal Runway Rehabilitation is currently scheduled for October 14, 2018.  The Airport will close Runway 18/36 during the crack and seal project.  The project is projected to last two weeks.  Project Manager is Joe Sober with KSA and Construciton Manager is Charlie Bright with the Univesity of Oklahoma.  The bid was awarded to Tri City Seal Company from Tuttle, Oklahoma. 

The two week time period is expected to be an ample amount of time for the crack seal project to be completed.  The airport will remain open during the entire constructin project.  However, runway 18/36 will be closed due to potential safety issues.  Please check NOTAMS daily for update information.  

Beacon Replacement

March 5, 2018

Refurbish beacon

Future Projects

2019 Project

Rehabilitation of the Parallel Taxiway System Runway 18/36 and 3/21

The proposed project includes rehabilitation the parallel taxiway system at Max Westheimer Airport.  The main taxiways to be rehabilitated are Taxiways Alpha, Bravo, and Charlie.  Additional connecting taxiways A1, C1, Delta and Echo will also receive rehabilitation durng this project.  These taxiways provide acess to both Runway and 18/36 and 3/21, as well as to the Terminal Apron and surrounding hangars.

This project will require comprehensive phasing and coordination between the airport, tenants, contractor and engineer to ensure that the airfield will be impacted as minimal as possible.  The rehabilitation of Parallel Taxiway System to Runway 18/36 and 3/21 will be broken into three phases of work with the work starting in FY 2019.

 

Past Projects

2015 Project

Rehabilitation of Runway 3/21

Runway 3 rehabilitation

This project consisted of improvements filling of cracks, replacement of 3.5" of alspalt. Durning the process, new drainage structures and grading were done in order to replace old drainage channels from the safety areas of both runway ends.  In addition, the project included the remarking and reddesignation of Runway 17/35 and 18/36 as well as the sealing and remarking of the runway.   

2014 Projects

Airport Garage
Garage to house the Airport Truck and Kobota
New Water Line
New water line placed at hanger 1200
Detention Pond
Detention Pond
Building 210 Clean-up
Clean-up outside of Building 210.
construction_of_hangar_connection
Construction of hangar connection for Hunter-Miller Company's hangar.
The Green Tanks
The green tanks that were removed at Building 210.

2013 Project

Replacement of Gate 6

Gate 6
Work being done on the replacement of Gate 6.

2012 Projects

This was a busy year for the airport with many projects.

  • Installation of the new AWOS system
  • Installation of the Windsock
  • Installation of the emergency vehicle entrance
  • Replacement of the airfield parking and lanes next to the terminal on the airfield
  • Pavement repair to the airfield
  • Line Shack demolition
  • Flood Lights installed
  • Building of  a new residental hanger
  • Controller box installation at Gate 7

 

2011 Projects

In 2011 PAPI was installed at RWY 35.  During that same year the fuel farm recieved some updates to the fueling area.  In that same year a road was installed by the north windsock.