PeopleSoft/Oracle Update

 

ORA's database management system will be "under construction" over the next 18 months as we transition from ACCESS to PeopleSoft's Grants Suite of modules. This transition will involve converting our data fields into the PeopleSoft environment. Another very labor intensive part of the process will be retooling the ORA office so that we most accurately and effectively use the modules, while ensuring that information can be accessed and extracted by users who rely on our office for information.

 

 This transition will utilize many of ORA's already limited resources; however, the transition and change is necessary in order for ORA to better serve the HSC campus.

 

We appreciate your patience during this transition period.

PeopleSoft Transition Teams

Pre-Award Transition Team

Mary Cotter-Lalli - Team Lead

Kasie Nichols

Lisa Asch

Post-Award Transition Team

Tamie Franklin - Team Lead

Janetta Tesch

Laurie Price

Shannon Kennedy

Frank Schwartzott

PeopleSoft Transition Milestones

The table below represents estimated milestones that the teams will be striving to meet to stay on schedule and budget during the transition. These dates are subject to change.

Transition KickoffFebruary 2009
Fit GapMarch 2009
AnalysisApril-May 2009
DesignJune 2009
DevelopmentJuly-September 2009
Testing and Data ConversionOctober 2009-March 2010
ImplementationApril-June 2010
GO LIVE!July 1, 2010

Project News & Updates

For up-to-date information on this project, you can visit www.ouhsc.edu/grants/.

 

Do you have questions about the Grants Project? Check to see if we've answered them, here.

 

July 31, 2009 Newsletter

 

November 3, 2009 Newsletter