PROJECT STATUS

The following chart outlines the basic milestones of this project and the status of those milestones.

Status Milestone
Complete Form Student Mail Project Team
Complete Review Possible Mail Solutions
Complete Select Mail System
Complete Begin Testing and Development on In-House pre-production equipment
Complete Plan Project Timeline
Complete Develop and Implement Communications Plan
Complete Accept Registration for Transfer Options
Complete Spec Out Equipment and Resources
Complete Procure Equipment
Complete Configure Equipment and Finalize Production Server
Complete Test Production Server
Complete Move Test Group Into Production
Complete Transfer Exchange 2003 Users to Exchange 2007
Complete Move all students using the student mail system who selected exchange it! or did not make a selection to Exchange 2007
Complete Transfer faculty, staff, and those who selected transfer it! to Exchange 2007
May 21, 2008 Disable the OU Mail system